5. ActivityBridge

How to allocate a Resource to an activity

Updated on

If you have resources  which are used in multiple activities, you should apply the Use Resource availability method.  Examples include vehicles, yachts, fields etc.

Choose Use Resource as the Availability Method for an activity

Click Settings.

Click Change existing activity.

Select the activity.

  1. Choose the Use Resource Availability Method.
  2. Click to Save.

Link the Resource to the activity

Click Settings.

Click Add/Edit Resources/Guide.

Click on a resource.

  1. Add the availability for an activity.
  2. Save

The system will automatically allocate resources to linked activities and block off activities that do not have a resource available.  

Previous Article How to allocate a Guide to an activity
Next Article How to hide a Pax Category online